The Department of Energy is procuring the supply, installation, and testing of a stainless-steel pipeline for transporting approximately 40,000 metric tons of Argon as part of the DUNE experiment. Key requirements include the construction of an 8” and 6” diameter pipeline from the Argon Receiving Facility to the Central Utility Cavern.

Generated 61d ago

Scope & Requirements

The work involves the supply, installation, and testing of a stainless-steel pipeline for transporting Argon from the surface to the Central Utility Cavern as part of the DUNE experiment.

Contract Details

Estimated Value
est. $73K – $19M
Place of Performance
Batavia, IL, USA

Agency & Contact

Contracting Organization

Agency
ENERGY, DEPARTMENT OF
Sub-Agency
ENERGY, DEPARTMENT OF
Office
FERMILAB - DOE CONTRACTOR

Point of Contact

John A. Smith
Contracting Officer
(202) 555-0100

Key Dates

Published2mo ago
Apr 1, 2026
Last Updated2mo ago
Apr 1, 2026
Became Presolicitation2mo ago
Apr 1, 2026
Tracked
Became Solicitation2mo ago
Apr 1, 2026
Tracked
Response Due2mo ago
Apr 9, 2026
Response Date1mo ago
Apr 30, 202615:00
CDT

Description

As part of the DUNE experiment, approximately 40,000 metric tons of Argon is required to be transported from the surface to the Central Utility Cavern (CUC) at the 4850 Level. This Argon will arrive at the Ross Shaft Argon Receiving station in liquid form where it will be stored in tanks. It will then be converted to the gaseous phase, where it will be transported underground through a stainless-steel pipeline. This pipeline will be 8” diameter Schedule 10 between the Argon Receiving Facility and the Ross shaft, 6” diameter schedule 10 from Ross shaft collar to the 4850 Level, then return to 8” diameter schedule 10 from the Ross shaft to the CUC. This SOW defined as “Argon Gas Piping Supply and Installation for LBNF” outlines the

requirements for the supply, installation and testing of a stainless-steel pipeline at LBNF as described above Jerry King Contracting . & Pine St. (No Street Address

2) Batavia, IL 60510 USA to this opportunity.